Mission Planning Checklist¶
Mission title / ID: _____________________________________________
PI / Science Lead: ________________________ Glider S/N: _______________
Planned deployment date: _______________ Planned duration: _________
Date of this review: _______________ Reviewer: ___________________
1. Mission Objectives¶
- Primary science objective defined and recorded in mission plan
- Required track and/or area of operation specified
- Required sensors identified and confirmed available
- Science sampling configuration defined (depth range, yo rate, sampling interval)
- Mission duration and endurance requirements calculated
- Secondary / opportunistic objectives identified and prioritised
- Mission plan signed off by both Science Lead and Glider Logistics Lead
2. Area of Operations¶
- Operational boundary polygon defined and recorded
Tides
- Tidal range and current speeds assessed for the deployment area
- Tidal phasing considered in track design and surfacing timing
- Tidal effects on ballasting target reviewed
Shipping lanes
- Shipping lane positions identified (marinetraffic.com or equivalent)
- Track designed to minimise time in high-traffic corridors
- AIS monitoring plan confirmed for duration of mission
Recreational traffic
- Recreational boating, sailing, and water-sports activity in area assessed
- Proximity to marinas, race courses, and popular anchorages checked
- Seasonal recreational patterns considered for deployment timing
Fishing grounds
- Active fishing grounds, trawl corridors, and longline areas identified
- Local fisheries authority or fishing association contacted where relevant
- Piloting strategy for minimising bottom time in trawled areas confirmed
Bathymetry & sea floor characteristics
- Accurate bathymetry chart sourced and reviewed for the full track
- Minimum water depths along track confirmed adequate for planned dive depth
- Seamounts, pinnacles, and steep slope areas identified
- Altimeter target altitude set with appropriate margin for local seabed roughness
- Bottom sediment type noted where relevant (soft vs. hard — affects bottom-strike risk)
- Abort waypoints and emergency recovery areas identified along the track
Other hazards
- Active military exercise areas checked (NOTMARs reviewed)
- Subsea cables, pipelines, and aquaculture installations reviewed
- Marine Protected Area boundaries checked; operating conditions confirmed
3. Risk Assessment¶
- Risk assessment document written or updated for this mission
- Environmental risks identified and mitigation measures defined
- Technical risks identified (glider age, sensor reliability, battery state)
- Operational risks identified (vessel availability, personnel coverage, comms gaps)
- Insurance availability assessed and arranged if required
- List of potential emergency recovery vessels and contact points compiled
- Contingency plan documented (back-up glider, emergency recovery procedure)
- Risk assessment reviewed and signed off by Mission Lead
4. Glider & Sensor Preparation¶
- Maintenance and calibration history reviewed; any preemptive service identified
- Sensor calibration status confirmed current for all payload sensors
- Ballasting target calculated using local water density data (CTD, models, or historical records)
- Ballasting data source recorded: ___________________________________
- Previous mission notes reviewed for oddities, setting changes, or unresolved faults
- Glider labels and contact information checked / updated
- Pre-deployment lab test slot confirmed
5. Piloting & Communications Plan¶
- Piloting rota established for at least the first deployment phase
- Experienced pilot confirmed for launch and first dives
- Escalation contact list prepared and distributed to all pilots
- Missed-call protocol defined (number of missed calls before escalation)
- Communication method between pilot and field team agreed and tested
- Satellite communication tested with vehicle (link confirmed)
- Shore-side monitoring schedule documented
- Piloting alert system verified
6. Logistics¶
- Deployment vessel confirmed and booked
- Staff travel and accommodation arranged
- Equipment shipping arranged (domestic / international as applicable)
- Dangerous goods certification confirmed for lithium battery shipment
- ATA carnet prepared if applicable
- Third-party recipients of hazardous goods notified
7. Regulatory & Notifications¶
- Diplomatic clearance obtained (international deployments): ref _____________
- NOTMAR / Notice to Mariners filed: ref _____________________________
- Coastguard notification submitted: ref _____________________________
- Research permits / environmental authorisations obtained: ref ____________
- Harbour master notified (if deploying from port): ref ___________________
- All confirmation receipts archived in mission folder
8. Data & Metadata¶
- Data flow set up with regional Data Assembly Centre (DAC)
- Minimum OceanOPS metadata fields completed (programme, WMO ID, PI, deployment position, agency, sensor models, glider model, serial number)
- Metadata submitted to OceanOPS ahead of deployment
- File naming conventions and repository structure confirmed with DAC
- Automated data transfer tested end-to-end
9. Final Review¶
- Mission plan reviewed by a team member not involved in its preparation
- All team members briefed on plan, contingencies, and abort criteria
- Health & Safety briefing completed; SOP signed by all personnel
- Mission plan archived in designated location
- Go / No-Go authority confirmed: ___________________________________
Sign-Off¶
| Role | Name | Signature | Date |
|---|---|---|---|
| Science Lead / PI | |||
| Glider Logistics Lead | |||
| Pilot (Launch) | |||
| Reviewer |
Mission Planning Checklist — v1.0